Weather just warm enough to pave SB lanes in Phase 1 of Centennial rebuild
The contractor, Kiewit Infrastructure Co., needs “three good days,” according to Ryan Phipps, the project manager for City Engineering, to pave the two southbound lanes between Garden of the Gods Road and Chesham Circle, The hope is that the other two days will come right afterwards, said Joe Garcia, who oversees the Centennial work on-site through city-contracted Wilson and Co. “We're trying to get it done before the weather turns really bad,” he said.
Started in early September, the current work is the first of three phases in a $9 million Pikes Peak Rural Transportation Authority project to rebuild/repave the four-lane Centennial between GoG Road and Fillmore. The city adheres to Pikes Peak Regional Asphalt Paving Specifications in deciding whether it's warm enough to put down asphalt, Phipps said. If the ground (“subgrade”) is too cold, the asphalt won't set properly. A specialized gauge is able to measure the subgrade temperature, and by 11 a.m. Nov. 30, with the help of mostly sunny skies, it was warm enough, Garcia said. Paving the southbound lanes fulfills the city's minimum Phase 1 goal as stated earlier this year. The hope then was that both northbound and southbound lanes of the 2,200-foot segment GoG Road-to-Chesham segment could get paved by the end of 2016 but southbound at the very least. The overall paving plan is to lay down two “sublayers” of 3 inches, topped by a final “lift” of 2 inches. The latest work
In early October, the expectation was that the final grading and concrete work would be done in time to allow paving to start by mid-November. There has been no rain or snow to slow things down, But a number of "little things" kept cropping up to cause delays, Garcia said. During Phase 1, the traffic in the work zone has been reduced to one lane each way, with vehicles in both directions temporarily using the northbound side. After the sublayer paving, the one-lane-each-way scenario will briefly continue, but in a different configuration, one that allows Kiewit to perform some work along the median. When that is done, work will stop for the winter and Kiewit will create a temporary four-lane configuration until spring. “All of this work is weather dependent, but we hope to have all four lanes open to traffic by the end of December,” Phipps said. Plans call for Kiewit to also complete the other two project phases in 2017.
Westside Pioneer article
Would you like to respond to this article? The Westside Pioneer welcomes letters at editor@westsidepioneer.com. (Click here for letter-writing criteria.) |